Council transformation savings hit by ERP implementation issues

Written by Colin Marrs on 12 January 2015 in News
News

Problems implementing a council’s enterprise resource system have shaved almost 10% off anticipated savings, according to a public sector spending watchdog.

Fife Council in Scotland signed a four year, £26m, deal with provider Capgemini in 2013 for the new system, aimed at providing the bulk of savings planned under a reorganisation of services.

However, a report by Audit Scotland for the council said that problems with delivering the ERP have been the main factor behind a 9.1% reduction in estimated savings from £53.6m to £48.7m in the period to 2019.

The report said: “Indications are that the programme will not achieve the benefits initially anticipated and there is a risk that the council might need to consider further budget reductions to achieve the savings target, potentially impacting on front-line services.”

The Oracle ERP is intended to transform the council’s financial management system.

However, the report revealed that changes to business processes and systems, such as validation checks over data transfer for ordering and receipts has not functioned properly.

When the system went live, this caused additional costs, delayed payments to suppliers, and a loss of confidence.

In addition, the council has been forced to employ temporary staff to rekey information due to other legacy software remaining in place.

Separate databases are in still in use for the different software, which the report said would mean additional effort would be needed when analysing data.

Future software updates will also be “more complex and expensive” because links between different systems will need to be tested and updates carried out.

“Had the programme started afresh, with no ongoing projects, rationalisation of the technologies could have been considered,” the report said.

The lack of efficient data transfer between systems has resulted in the postponement of £86,000 of anticipated benefit from an “improved accounts payable and procurement linkage” and £363,000 of anticipated benefit from “financial management & analytics”. There is a risk that some of these benefits may not actually be realised.”

Management at the council has admitted that there was insufficient detailed understanding of the processes that required change to fit into the ERP model before training on the new system was delivered.

The council has now slowed down the implementation of the ERP in order to allow staff and other users to gain more confidence in it.

It has also agreed a 10-point action plan in an attempt to get the transformation back on track.

Share this page

Tags

CONTRIBUTIONS FROM READERS

Please login to post a comment or register for a free account.

Comments

Gareth (not verified)

Submitted on 23 January, 2015 - 09:26
Presumably the audit report is available to the public, can you provide a link?

ColinMarrs

Submitted on 25 January, 2015 - 17:07
Hi Gareth - Try this link - it should directly download a pdf. Colin Marrs, PublicTechnology.net http://www.fifedirect.org.uk/uploadfiles/publications/c64_PDF-SA-080115.pdf

Joe (not verified)

Submitted on 21 May, 2015 - 11:28
But nobody cares - because it's somebody else's money. Fill your boots. F it up. Fill your boots again.

Related Articles

BEIS develops regulatory database after post-Brexit loss of access to EU platform
25 November 2021

Regulated Professions Register will provide information for authorities, professional users and policymakers

Criticism of spending on Covid schemes ‘slightly unfair’ – Sunak
3 November 2021

Chancellor appears before MPs to answer questions about value for money and efficacy of programmes include Test and Trace and the furlough scheme

Calls for home secretary to shed light on deal to store top-secret spy data in AWS cloud
28 October 2021

Critics claim potential £1bn contract is ‘deeply concerning’, but former NCSC head describes move as ‘perfectly sensible decision’